Before heading out onsite, XYZ planners and site engineers link the 3D model to the construction schedule. This integration allows for a clear visualization of planned versus actual progress, providing a detailed picture of how the project is advancing compared to the initial plan.
Between November 2022 and September 2023, the engineers conducted 821 surveys. 77 of these surveys identified issues that, if not corrected immediately, would have delayed the project’s progress and led to costly rework.
By catching these errors early, the contractor avoided the need for additional project hours and resources. Taking proactive measures to prevent delays and costs enabled the project teams to construct faster and more accurately, ensuring quicker delivery of the mission critical asset – and quicker revenue generation.