Turbocharged construction timelines with real-time project controls
To accelerate the completion of their pharma build and shorten the length of time before it could start manufacturing, the general contractor enlisted XYZ’s support.
Over a ten month period, the contractor benefitted from XYZ’s fully-managed service to ensure accuracy and confidence as the asset handover date grew closer. Objective and precise data, gathered by two XYZ Field Application Engineers (FAEs), offered up invaluable insights that made the project run smoother and more streamlined at every stage.
XYZ’s FAEs conducted hundreds of surveys across areas selected by the main contractor. Using the AtomTM, XYZ’s powerful custom-built engineering tool, the FAEs and onsite teams deployed highly accurate holograms of 4D BIM to visualize and compare real-time construction progress with the program schedule, effectively identifying discrepancies.
Before heading out onsite, XYZ planners and FAEs link the 3D model to the construction schedule. This integration allows for a clear visualization of planned versus actual progress, providing a detailed picture of how the project is advancing compared to the initial plan.
Between November 2022 and September 2023, the FAEs conducted 821 surveys. 77 of these surveys identified issues that, if not corrected immediately, would have delayed the project’s progress and led to costly rework.
By catching these errors early, the contractor avoided the need for additional project hours and resources. Taking proactive measures to prevent delays and costs enabled the project teams to construct faster and more accurately, ensuring quicker delivery of the mission critical asset – and quicker revenue generation.